Do I need a permit to remodel my house in Florida?
Yes, in most cases you need a permit to remodel your house in Florida. Unless otherwise provided by law, it is against state law to build, change, repair or tear down any building without first getting a permit from the right enforcing agency.1 Ask your building department which permits your job needs.
Do I need a permit to remodel my house in Florida?
A building permit is written approval from your local enforcing agency to do a specific job on a building. Florida building permit requirements start with one statewide rule, and unless otherwise provided by law, it covers repairs and changes, not just additions.1
The details are local.
Call the permit office for your address before you sign anything, whether you live in Vero Beach or Winter Garden. For a shower, tub or full bath job, read our guide to permits for a bathroom remodel in Florida.
Can a handyman do the work without a permit?
Not usually. Florida’s handyman exemption covers only casual, minor or inconsequential work under $2,500 total, and DBPR says work that needs a permit typically does not qualify, whatever the price.234
A low price does not turn permitted work into handyman work. If you’re unsure, DBPR says to ask your local building department.4
Should I pull the permit myself as an owner-builder?
Think it through first. If you pull the permit as an owner-builder, you become the responsible party of record.2 You must also provide direct, onsite supervision.2
The state’s own disclosure warns that unlicensed people often have owners pull owner-builder permits.2 If a contractor asks you to put the permit in your name, ask why.
Plans to sell matter too. Say you sell or lease a home you built or substantially improved within 1 year after the work is done.2 The law then presumes you did the work to sell or lease it, which breaks the exemption.2
What paperwork protects me from paying twice?
Lien law adds its own forms. They are dull, but they matter.
Before work begins, the owner (or an authorized agent) must record a notice of commencement unless the job is exempt under s. 713.02(5).5 If the direct contract is more than $5,000, the permit applicant must file a copy with the issuing authority before the first inspection.6
Permit cards must warn that failing to record one may mean paying twice.6
Your contract needs a warning too. A direct contract over $2,500 between an owner and a contractor must contain the statutory construction-lien notice when it covers a dwelling of up to and including four units.7 If it’s missing, ask before you sign.
Does a big remodel in a flood zone change the rules?
It can. FEMA defines substantial improvement as any rebuilding, rehab, addition or other improvement that costs 50 percent or more of the structure’s market value before construction.89
When a building in a mapped flood hazard area will be substantially improved, it must meet the floodplain rules for new construction.9 The local official makes that call, not your contractor.9
Some communities set a lower threshold, such as 40 or 30 percent, or add up improvement costs over a period of time.9 Ask your permit office how yours counts before you settle the scope.
How long does the permit decision take?
State law sets decision clocks. They apply only to listed permit types, and only when the applicant uses a local government plans reviewer.10
- Residential units on a structure under 7,500 square feet: the local government must decide within 30 business days of a complete and sufficient application.10
- Listed jobs on an existing single-family home with work under $15,000, such as structural, electrical, gas, mechanical, plumbing or roofing: the clock is 5 business days.10
The applicant can waive these timeframes in writing.10 They are not a general county deadline, and they are not your project timeline.
What should I ask a contractor before I sign?
Start with the license itself. Our guide on how to check a contractor license in Florida shows how. Then take these questions to every bid:
- Who is pulling the permit, and whose license number is on it? Registered and certified contractors must put their license number on any building permit application, plus bids, contracts and ads.3
- Will you ask me to pull an owner-builder permit? That would make me the responsible party of record.2
- How big is the deposit? If a contractor takes more than 10 percent of the contract price up front on residential work, they must apply for permits within 30 days (unless no permit is needed) and start work within 90 days after permits issue.11 A contractor’s just cause, or your written agreement to a longer period, can excuse these deadlines.11
- Who records the notice of commencement, and who files the copy before the first inspection?56
- Where is the construction-lien notice in this contract?7
FAQ
Is a small repair exempt from permits?
It can be: work under $7,500 on a single-family home may qualify for a permit exemption on written request, except in a flood hazard area or with electrical, plumbing, structural, mechanical or gas work.1 Orange County says it took effect July 1, 2026, and that exterior window and door replacements are structural, so they still require a permit.12 The handyman exemption is a separate licensing rule, not a permit exemption.2
Can the permit decision clock be waived?
Yes. The applicant can waive it in writing.10 The clocks cover only listed permit types when the applicant uses a local government plans reviewer.10
Does every big remodel trigger flood rules?
No. The new-construction flood rules apply when a building in a mapped flood hazard area will be substantially improved.9 The local official decides that.9
Does Howe.to check contractor licenses?
No. Howe.to does not check licenses, inspect work or give legal advice.
How Howe.to can help
To begin, start my remodeling request. Answer a few short questions about your project and choose which local companies may contact you about it. Howe.to is not a contractor, inspector, insurer or government agency. Keep the checklist above handy when companies reach out.